Project Duration
Stipulated Date of Commencement
October 21 2016
Stipulated Date of Completion /
Likely Date of Completion January 03 2017
Likely Date of Completion January 03 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,941,587.00
Awarded for
₹ 20,104,685.73
Project highlights
Renovation of office premises of Goa Public Service commission at 1st and 2nd floor of Block C of EDC House
Contractors
M/s.Vastu Sadan
Consultants
M/s. Nilesh Salkar Associates