Project Duration
Stipulated Date of Commencement October 21 2016
Stipulated Date of Completion /
Likely Date of Completion
January 03 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,941,587.00
Awarded for ₹ 20,104,685.73

Project highlights

Renovation of office premises of Goa Public Service commission at 1st and 2nd floor of Block C of EDC House

 
Gallery Image
Contractors
M/s.Vastu Sadan
Gallery Image
Consultants
M/s. Nilesh Salkar Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of High Court Complex at Penha de Franca, Porvorim.Civil, Plumbing, Electrical, HVAC, Lift and Firefighting works

View Project
Similar Project

HVAC work.

View Project
Similar Project

Construction of Forest Headquarters Building at Altinho Old IPHB Complex – Civil,Plumbing, Electrical,HVAC,Lifts and fire fighting works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.