Project Duration
Stipulated Date of Commencement
May 18 2020
Stipulated Date of Completion /
Likely Date of Completion May 17 2023
Likely Date of Completion May 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 938,385.00
Awarded for
₹ 938,385.00
Project highlights
AMC of HVAC System
Contractors
M/s. Voltas Limited
Consultants
In-house (GSIDC)