Project Duration
Stipulated Date of Commencement
February 12 2015
Stipulated Date of Completion /
Likely Date of Completion May 11 2015
Likely Date of Completion May 11 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,524,278.45
Awarded for
₹ 32,955,460.00
Project highlights
Upgraded premises for the Goa Human Resource Development Corporation at Porvorim, Goa
Contractors
M/s. Concept Creators
Consultants
M/s. Shiva Consultancy Services Pvt. Ltd.