Project Duration
Stipulated Date of Commencement
January 2 2016
Stipulated Date of Completion /
Likely Date of Completion August 1 2017
Likely Date of Completion August 1 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 151141272.59
Awarded for
₹ 157912311.00
Project highlights
The work of Promenade was executed from Youth Hostel to Kala Academy having 900 meter length with 4.5 m wide walkway & 2.5 m cycle track. Rip rap was provided to protect the coast. Selfie points & senior citizen park was renovated.
Contractors
M/s. Krishna Builder
Consultants
M/s. LKS India Pvt Ltd.