Project Duration
Stipulated Date of Commencement
November 16 2017
Stipulated Date of Completion /
Likely Date of Completion November 25 2017
Likely Date of Completion November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 221,757.00
Awarded for
₹ 203,630.00
Project highlights
The scope of work includes supply, installation, testing & commissioning of Chandelier at the Old GMC Building and Gate lights, Bollards at the Maquinez Palace.
Contractors
M/s. Fusion Events Ltd.
Consultants
M/s.Vaishali Pednekar Associates