Project Duration
Stipulated Date of Commencement
January 14 2019
Stipulated Date of Completion /
Likely Date of Completion November 22 2019
Likely Date of Completion November 22 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,684,590.19
Awarded for
₹ 14,543,893.00
Project highlights
Repair of Outpost premises for Excise Department. The renovated outpost premises of Excise Department , involves repair of ground and Mezzanine Floor. The project methodology involves adaptive reuse of this heritage structure including.
Contractors
M/s.Guru Construction
Consultants
M/s. Pankaj Joshi Consultant