Project Duration
Stipulated Date of Commencement January 15 2022
Actual Date of Completion January 23 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,21,63,584.00
Awarded for ₹ 1,15,42,715.00

Project highlights

Supply and installation of furniture work

 
Contractors
M/s. Amardeep Designs India (P) Limited
Consultants
M/s. Datta Kare Associates
 

See Similar Projects

Construction of Institute of Nursing Education Complex at Bambolim, Goa – Civil, Plumbing & Internal Electrical works

View Project

Furniture work.

View Project

“Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Supply, Installation, Testing and Commissioning of 11KV 4 Way outdoor type RMU and other allied works”

View Project