Project Duration
Stipulated Date of Commencement
January 12 2017
Stipulated Date of Completion /
Likely Date of Completion March 11 2017
Likely Date of Completion March 11 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 519,252.48
Awarded for
₹ 558,577.50
Project highlights
Supply, Installation, Testing and Commissioning of Defibrillator will provide track of heart functions for monitoring vital parameters for the new burns ward at GMC
Contractors
M/s. Summit Healthcare Pvt. Ltd.
Consultants
In-house (GSIDC)