Project Duration
Stipulated Date of Commencement November 11 2017
Actual Date of Completion December 20 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,680,476.00
Awarded for ₹ 15,562,927.50
Final Cost of Project ₹ 10,811,766.00

Project highlights

Resurfacing of roads in Panaji city for IFFI 2017

 
Contractors
M/s Assmas Construction
Consultants
M/s Vaishali Pednekar & Associates
 