Project Duration
Stipulated Date of Commencement January 14 2022
Stipulated Date of Completion /
Likely Date of Completion
April 13 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,695,125.00
Awarded for ₹ 2,072,768.94

Project highlights

Roofing works at Community Health Centre, Canacona

 
Gallery Image
Contractors
M/s.Aditya P. Kamat Tarcar
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Supplying and laying of 33 KV underground cable from Sub Station to District Hospital at Mapusa

View Project
Similar Project

Electrical works

View Project
Similar Project

Design, supply, erection, testing and commissioning of 5 Nos. pre-fabricated Modular Operation Theatres along with centralised medical gas pipe system within the 5 No. OTs at Goa Medical College & Hospital, Bambolim, Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.