Project Duration
Stipulated Date of Commencement
January 14 2022
Stipulated Date of Completion /
Likely Date of Completion April 13 2022
Likely Date of Completion April 13 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,695,125.00
Awarded for
₹ 2,072,768.94
Project highlights
Roofing works at Community Health Centre, Canacona
Contractors
M/s.Aditya P. Kamat Tarcar
Consultants
In-house (GSIDC)
See Similar Projects
Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa. SH : Maintenance of Split, Window Type, Mega split, Multi split and Tower type Air Conditioners installed in GMC Complex, Bambolim (2020-2023)
View Project
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College. S.H.: Supply, Installation, Testing & Commissioning of audio system for Autopsy Auditorium in the Forensic Block at Goa Medical College, Bambolim-Goa.
View Project
Demolition and construction of hospital and hostel at Mandur, Goa
View Project