Project Duration
Stipulated Date of Commencement September 01 2007
Stipulated Date of Completion /
Likely Date of Completion
November 15 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,221,765.00
Awarded for ₹ 16,545,265.00
 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators

View Project
Similar Project

Construction of subway at Bambolim

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Hospital Furniture, Kitchen Equipment and Interior works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.