Project Duration
Stipulated Date of Commencement
September 01 2007
Actual Date of Completion
September 30 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,221,765.00
Awarded for
₹ 16,545,265.00
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.