Project Duration
Stipulated Date of Commencement
January 10 2018
Stipulated Date of Completion /
Likely Date of Completion November 30 2018
Likely Date of Completion November 30 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 345,101.00
Awarded for
₹ 342,014.00
Project highlights
SITC of 2 Nos. 5.5TR ductable units for MRI section at Goa Medical College, Bambolim-Goa.
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Renovation/ Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Servicing of installed HVAC Water line for Chillers installed at Sub District Hospital, Ponda Goa
View Project
Supply, Installation, Testing and Commissioning of E. T. O Machine
View Project
Maintenance works at Goa Medical College and Hospital, including Hospitals and Health Centres under the jurisdiction of Goa Medical College S.H.:Supply, Installation, Testing and Commissioning of Audio Power Amplifiers for Lecture Halls 4, 5 & 6 at Goa Medical College
View Project