Project Duration
Stipulated Date of Commencement
October 01 2018
Stipulated Date of Completion /
Likely Date of Completion September 30 2021
Likely Date of Completion September 30 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,347,625.00
Awarded for
₹ 25,844,737.50
Project highlights
Carriage of water from Altinho to Bambolim
Contractors
M/s. Pedro Gomes
Consultants
In-house (GSIDC)
See Similar Projects
Repairs and Upgradation of roads and storm water drains around new Library Building, GMC Complex, Bambolim, Goa.
View Project
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri .SH- Upgradation of Wards Nos 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College & Hospitals at Bambolim ,Goa – Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim.- Office Furniture
View Project
Reconstruction / Upgradation of Primary Health Centre at Sanquelim, Goa -Civil & Plumbing work.
View Project