Project Duration
Stipulated Date of Commencement
July 05 2020
Stipulated Date of Completion /
Likely Date of Completion November 04 2024
Likely Date of Completion November 04 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 347,094.00
Awarded for
₹ 347,094.00
Project highlights
Maintenance of lift at GMC TB and Chest Diseases Hospital, St. Inez Goa
Contractors
M/s. Otis Elevator Company (India) Ltd.
Consultants
In-house
(GSIDC)