Project Duration
Stipulated Date of Commencement
December 26 2019
Stipulated Date of Completion /
Likely Date of Completion December 25 2024
Likely Date of Completion December 25 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 2,600,000.00
Awarded for
₹ 2,392,960.00
Project highlights
Maintenance of VRV air conditioning system at GMC
Contractors
M/s. Airflow Engineering,
Consultants
In-house
(GSIDC)