Project Duration
Stipulated Date of Commencement March 18 2019
Actual Date of Completion June 30 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 468,019.00
Awarded for ₹ 464,915.00
Final Cost of Project ₹ 440,224.00

Project highlights

Supply, Installation, Testing & Commissioning of Tower air conditioning units for the Reading room in the Library at Goa Medical College.

 
Contractors
M/s. Vighneshwar Airconditioning Pvt. Ltd.
Consultants
Inhouse (GSIDC)
 