Project Duration
Stipulated Date of Commencement
April 23 2012
Actual Date of Completion
February 18 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,62,97,694.73
Awarded for
₹ 7,06,63,484.94
Final Cost of Project
₹ 66,565,103.00
Contractors
M/s. Shilpi Constructions, M/s. Shilpi Constructions
Consultants
M/S. FRISCHMANN PRABHU (INDIA) PVT. LTD., M/S. FRISCHMANN PRABHU (INDIA) PVT. LTD.
See Similar Projects
Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa.
View ProjectRepairs / Upgradation & Maintenance of Old Primary Health Centre at Sanquelim, Goa – Civil, Plumbing & Electrical works
View ProjectUpgradation of Casualty, Trauma Ward and reception areas in Goa Medical College at Bambolim,Goa. – Civil and plumbing work.
View Project