Project Duration
Stipulated Date of Commencement April 23 2012
Actual Date of Completion February 18 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,62,97,694.73
Awarded for ₹ 7,06,63,484.94
Final Cost of Project ₹ 66,565,103.00
 
Contractors
M/s. Shilpi Constructions, M/s. Shilpi Constructions
Consultants
M/S. FRISCHMANN PRABHU (INDIA) PVT. LTD., M/S. FRISCHMANN PRABHU (INDIA) PVT. LTD.
 