Project Duration
Stipulated Date of Commencement
January 18 2019
Stipulated Date of Completion /
Likely Date of Completion February 17 2019
Likely Date of Completion February 17 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 253,724.00
Awarded for
₹ 246,850.00
Project highlights
SITC of audio system for Autopsy Auditorium in the Forensic Block at Goa Medical College, Bambolim-Goa.
Contractors
M/s. Geeta Automation Technologies
Consultants
In-house (GSIDC)
See Similar Projects
Electrical & Fire Fighting work.
View Project
Commissioning, operation & maintenance of Sewage Treatment Plant at Subdistrict Hospital at Ponda, Goa.
View Project
Supply of Syringe pumps
View Project