Project Duration
Stipulated Date of Commencement October 12 2018
Stipulated Date of Completion /
Likely Date of Completion
September 02 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,127,060.00
Awarded for ₹ 1,823,808.00

Project highlights

SITC of 30KVA online UPS systems for ICU 123 and Modular OT 5 at Goa Medical College.

 
Gallery Image
Contractors
M/s. Power Resources,
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Echo machines.

View Project
Similar Project

Medical gas & vacuum plant.

View Project
Similar Project

Providing of split air conditioners.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.