Project Duration
Stipulated Date of Commencement
November 10 2017
Stipulated Date of Completion /
Likely Date of Completion November 09 2020
Likely Date of Completion November 09 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 908,724.00
Awarded for
₹ 908,724.00
Project highlights
Maintenance of UPS systems at GMC
Contractors
M/s. Vertiv Energy Pvt. Ltd.,
Consultants
In-house (GSIDC)