Project Duration
Stipulated Date of Commencement
March 05 2014
Stipulated Date of Completion /
Likely Date of Completion August 04 2014
Likely Date of Completion August 04 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,506,358.95
Awarded for
₹ 32,467,272.50
Project highlights
Maintenance of bridges (North Goa)
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.,
Consultants
Pre tender – M/s. Kashec Engineers Pvt. Ltd.,
Post tender – In-house (GSIDC)
Sub Works
This project involved 1 sub works. The details of the same available below
1
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) -Electrical work
100% completed
Project Duration
Stipulated Date of Commencement
March 05 2014
Stipulated Date of Completion /
Likely Date of Completion August 04 2014
Likely Date of Completion August 04 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 25,219,798.80
Awarded for
₹ 26,356,358.00
Project highlights
Maintenance of bridges
Contractors
M/s.Goa Friends Engineering & Electrical Pvt. Ltd.
Consultants
In-house (GSIDC)
See Similar Projects
Design and Construction of Nuem – Cola Bridge including approach road in Canacona Taluka.
View Project
Construction of vehicular bridge at Hedode including approaches in Sattari, Goa.
View Project
Construction of Bridge across Rua de Ourem Creek, Panaji
View Project