Project Duration
Stipulated Date of Commencement
February 09 2018
Stipulated Date of Completion /
Likely Date of Completion February 15 2021
Likely Date of Completion February 15 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,732,383.00
Awarded for
₹ 3,732,383.00