Project Duration
Stipulated Date of Commencement February 16 2010
Stipulated Date of Completion /
Likely Date of Completion
June 15 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,960,000.00
Awarded for ₹ 20,00,000.00
 
Gallery Image
Contractors
M/s. Thyssenkrupp Elevators (P) Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Echo machines.

View Project
Similar Project

Upgradation of Community Health Center at Cacora, Curchorem

View Project
Similar Project

Construction of Day Care Centre at Instuitute Psychiatry and Human Behaviour Complex (IPHB), Bambolim Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.