Project Duration
Stipulated Date of Commencement
October 28 2016
Stipulated Date of Completion /
Likely Date of Completion January 27 2017
Likely Date of Completion January 27 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 39,893,986.00
Awarded for
₹ 36,930,164.00
Project highlights
Soft and hard landscaping work in the gardans and along DB Road
Contractors
M/s. Green Mek Hortitek Pvt. Ltd.
Consultants
M/s. Shobha Bhopatkar
See Similar Projects
Cortalim to Verna via Airport – 24.00 km.
View Project
Renovation of GSIDC office premises on 7th & 8th floor of EDC House, Panaji Goa.
View Project
Reconstruction/Repair of Excise Outpost Kiranpani, Paliem, Pernem, Goa – Interior & Furniture Works
View Project





