Project Duration
Stipulated Date of Commencement
March 30 2013
Stipulated Date of Completion /
Likely Date of Completion June 29 2013
Likely Date of Completion June 29 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,728,163.00
Awarded for
₹ 1,946,075.00
Project highlights
Providing of lawn and different types of plants around Ravindra Bhavan.
Contractors
M/s. Vrindavan Agricultural Services
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.