Project Duration
Stipulated Date of Commencement
March 04 2014
Stipulated Date of Completion /
Likely Date of Completion May 03 2014
Likely Date of Completion May 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 41,947,211.00
Awarded for
₹ 37,397,572.00
Project highlights
Furniture work
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Banaji & Associates