Project Duration
Stipulated Date of Commencement
February 15 2014
Stipulated Date of Completion /
Likely Date of Completion May 15 2014
Likely Date of Completion May 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,914,384.00
Awarded for
₹ 31,007,908.28
Project highlights
Providing interior furniture, false ceiling, parttions and other furnishings
Contractors
M/s. T. S. Mistry,
Consultants
M/s. KICONS Limited