Project Duration
Stipulated Date of Commencement November 19 2016
Actual Date of Completion October 11 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 23,247,293.00
Awarded for ₹ 20,634,341.00
Final Cost of Project ₹ 20,634,341.00

Project highlights

13 Incubation offices with total 48 work stations completely air-conditioned with VRV air-conditioning.
Two six seater Conference rooms
Network Operation Centre (NOC) with UPS, VRV Air conditioning (AC), split back up AC and 100% Diesel Generator Backup for (NOC)
STPI Managers office
Two toilet blocks and one VIP toilet
Two waiting areas and one reception area
Cafe with informal working and relaxing spaces
Entrance Lobby, Pantry, Staircase and Lift block

 
Contractors
M/s. Dovetail Projects India Pvt. Ltd.
Consultants
M/s. Pankaj Joshi Consultants
 

See Similar Projects

Air conditioning works.

View Project

Integration of Renovation of Ravindra Bhavan & Construction of IInd Phase of Ravindra Bhavan at Curchorem-Goa, Construction of Sports Complex at Curchorem-Goa, Construction of Bus Stand at Curchorem with related Infrastructure and CCMC Admin Building at Curchorem.

View Project

Interior work for branch office of Directorate of Food and Drugs Administration in Old Collectorate building, Margao, Goa

View Project
x