Project Duration
Stipulated Date of Commencement February 16 2015
Actual Date of Completion March 15 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,698,000.00
Awarded for ₹ 1,739,000.00
Final Cost of Project ₹ 1,739,000.00

Project highlights

Supply of fabricated custumized toe cranes

 
Contractors
M/s. Chowgules Industries Pvt. Ltd.
Consultants
Inhouse
 