Project Duration
Stipulated Date of Commencement July 11 2014
Stipulated Date of Completion /
Likely Date of Completion
August 10 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,76,42,076.00
Awarded for ₹ 19,688,390.00
 
Gallery Image
Contractors
M/s. Floor-Space
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Area Lighting for Exposition 2014 at Old Goa

View Project
Similar Project

Supply and erection of new 11KV line with AB conductor from 33/11KV colony substation to M/s.Rajiv Gandhi Kala Mandir

View Project
Similar Project

Construction of Community Hall in the Morlem Rehabilitation Colony in Sattari Taluka

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.