Project Duration
Stipulated Date of Commencement September 29 2013
Stipulated Date of Completion /
Likely Date of Completion
December 28 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,782,048.00
Awarded for ₹ 17,220,980.50

Project highlights

Providing of loose furniture, false ceiling, panelling etc. in the the building.

 
Gallery Image
Contractors
M/s. Floor-Space
Gallery Image
Consultants
M/s. Frischmann Prabhu (India) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Repairs and Upgradation of solid waste management facilities within the jurisdiction of CCP in Panjim City – Civil Works

View Project
Similar Project

Construction of Sanskruti Bhavans for Department of Tribal Welfare at Baradi, Velim, Salcete.

View Project
Similar Project

Renovation of GSIDC office premises on 7th & 8th floor of EDC House, Panaji Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.