Project Duration
Stipulated Date of Commencement July 29 2008
Stipulated Date of Completion /
Likely Date of Completion
December 28 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 22,614,408.61
Awarded for ₹ 22,424,910.00

Project highlights

False ceiling, reception counters, work table counters, modular furniture items for library such as book racks, tables, work stations etc.

 
Gallery Image
Contractors
M/s. Concept Creators
Gallery Image
Consultants
M/s. Architecture Autonomous / M/s. Mahimtura Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Ravindra Bhavan at Baina, Vasco, Goa

View Project
Similar Project

Construction of Multipurpose Hall and office building for Village Panchayat, Salvador do Mundo – Phase I Land Development.

View Project
Similar Project

Providing and Maintaining Event Management facilities for Exposition 2014 at Old Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.