Project Duration
Stipulated Date of Commencement
July 26 2018
Stipulated Date of Completion /
Likely Date of Completion March 25 2019
Likely Date of Completion March 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,100,310.00
Awarded for
₹ 31,895,244.00
Project highlights
Interior works for Sanjay School building at Vasco & Porvorim which includes new modular furnitures for special childrens, carpentary works, new stage along with acoustics etc.
Contractors
M/s. Macro Enterprises
Consultants
M/s Rajesh Kenkre
See Similar Projects
Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Sanguem Taluka – (GPS Periudak, GPS Devnamol, GPS Mugoli, GPS Taripanta, GPS Curpem)
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Ponda Taluka: GPS Volvoi & GPS Veling
View Project
Repairs/ Upgradation & Maintenance of Government Primary Schools in the State of Goa: Dharbandora Taluka – Package II (GPS Surla, GPS Dharge, GPS Udlashem, GPS Kumbharwada)
View Project