Project Duration
Stipulated Date of Commencement
October 05 2020
Stipulated Date of Completion /
Likely Date of Completion November 04 2020
Likely Date of Completion November 04 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 236,180.00
Awarded for
₹ 189,250.00
Project highlights
Providing fire safety and exit signages work
Contractors
M/s. R K Infra
Consultants
In-house (GSIDC)