Project Duration
Stipulated Date of Commencement
March 14 2019
Stipulated Date of Completion /
Likely Date of Completion June 13 2020
Likely Date of Completion June 13 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 48,103,670.66
Awarded for
₹ 50,883,616.81
Contractors
M/s. Dalavai Infrastructure
Consultants
M/s. Bhaskar Wagle & Associates