Project Duration
Stipulated Date of Commencement November 16 2014
Actual Date of Completion July 20 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 64,849,555.41
Awarded for ₹ 88,449,597.00
Final Cost of Project ₹ 88,449,597.00

Project highlights

School building consist of G+3 RCC structure with independent Ramp and also Various rooms such as administrative offices, vocational training halls etc.

 
Contractors
M/s M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s Archvista Engg. Privt. Limited
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Infrastructure works for Sanjay Centre for Special Education at Bogda, Vasco – Electrical, Lift and Fire Fighting Works

100% completed
 
Project Duration
Stipulated Date of Commencement July 06 2016
Stipulated Date of Completion /
Likely Date of Completion
July 15 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,596,091.00
Awarded for ₹ 13,646,379.00
Final Cost of Project ₹ 13,249,102.00

Project highlights

Electrical, Lift and Fire Fighting Works

 
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd
Consultants
M/s. Archivista Engineering Projects Pvt.Ltd.

See Similar Projects

Construction of new Government Primary and Secondary Schools in the State of Goa – GHS at Honda, GPS at Bhironda and GHS at Guleli in Sattari taluka.

View Project

Furnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka

View Project

Construction of Football ground at Zariwada, Davorlim, Dicapale, Salcete Goa”.

View Project