Project Duration
Stipulated Date of Commencement August 18 2009
Stipulated Date of Completion /
Likely Date of Completion
February 17 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 61,06,052.00
Awarded for ₹ 7,020,395.00
 
Gallery Image
Contractors
M/s. Japsin Jacob Wire Drawing Pvt. Ltd.
Gallery Image
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Lecture Hall Elevator and Girls Hostel Elevator installed at Goa Medical College and Hospital, Bambolim for three years (2018-2021).

View Project
Similar Project

Upgradation of Pay Ward at Goa Medical College, Bambolim, Goa – Additional furniture works

View Project
Similar Project

Supply & installation of trays and sliding mechanism for mortuary cabinets.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.