Project Duration
Stipulated Date of Commencement
December 12 2011
Stipulated Date of Completion /
Likely Date of Completion April 11 2012
Likely Date of Completion April 11 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,528,636.00
Awarded for
₹ 5,976,204.30
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Supply, Installation, Testing & Commissioning of Mortuary Cabinet.
100% completed
Project Duration
Stipulated Date of Commencement
December 01 2011
Stipulated Date of Completion /
Likely Date of Completion March 31 2012
Likely Date of Completion March 31 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,058,320.00
Awarded for
₹ 2,406,250.00
Contractors
M/s. Megastar Engineering
Consultants
M/s. Datta Kare Associates
See Similar Projects
Shadowless lights.
View Project
SITC of medical gas supply system (MGSS)
View Project
Supply, Installation, Testing and Commissioning of Cardiac output Monitoring System
View Project