Project Duration
Stipulated Date of Commencement
July 02 2010
Actual Date of Completion
December 31 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,064,138.00
Awarded for
₹ 2,909,220.00
Final Cost of Project
₹ 3,199,459.00
Project highlights
False ceiling works
Contractors
M/s. Deshpande Constructions
Consultants
M/s Effective Architectural Services