Project Duration
Stipulated Date of Commencement March 17 2009
Actual Date of Completion October 31 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 33,782,875.00
Awarded for ₹ 34,574,345.00
Final Cost of Project ₹ 7,785,539.00

Project highlights

Repairs works

 
Contractors
M/s. Kanaka Infratech Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 