Project Duration
Stipulated Date of Commencement
August 26 2011
Actual Date of Completion
August 13 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,725,185.00
Awarded for
₹ 3,581,610.75
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Effective Architectural Services