Project Duration
Stipulated Date of Commencement
June 15 2011
Actual Date of Completion
August 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,609,226.00
Awarded for
₹ 6,841,664.00
Contractors
M/s. Power & Instrumentation (Guj) Ltd.
Consultants
M/s. Keni & D’Souza