Project Duration
Stipulated Date of Commencement April 01 2013
Actual Date of Completion May 05 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,523,900.00
Awarded for ₹ 1,447,436.09
Final Cost of Project ₹ 1,656,771.00

Project highlights

Fabrication and supply of metal cages of size 1.37 m X 1.40 m X 1.22 m.

 
Contractors
M/s. Rakesh Kambli, M/s. Rakesh Kambli
Consultants
Inhouse, Inhouse
 