Project Duration
Stipulated Date of Commencement December 23 2005
Stipulated Date of Completion /
Likely Date of Completion
February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 526,300.00
Awarded for ₹ 678,618.00

Project highlights

The work includes external electrical works

 
Gallery Image
Contractors
M/s. Ohm Engineers
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Conversion of Pedestrian Subway to Motorable Subway at Bambolim, Goa – Civil, Plumbing & Electrical works

View Project
Similar Project

Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for the Passenger Elevator and Dumb waiter installed in the Library Block at Goa Medical College and Hospital, Bambolim for three years.

View Project
Similar Project

Face-lift to Tisk Usgao Hospital building including staff quarters

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.