Project Duration
Stipulated Date of Commencement March 26 2007
Actual Date of Completion June 24 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,548,209.00
Awarded for ₹ 9,552,600.00
 
Contractors
M/s. NAT Steel Equipment
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 