Project Duration
Stipulated Date of Commencement February 24 2014
Actual Date of Completion July 07 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,221,634.00
Awarded for ₹ 2,113,317.73
Final Cost of Project ₹ 2,252,110.00

Project highlights

Supply, Installation, Testing and Commissioning of CCTV, Biometric attendance and PA system

 
Contractors
M/s. Reconnoitre Systems
Consultants
M/s. KICONS Pvt. Ltd.
 

See Similar Projects

Urgent Repairs/Renovation to Police Outpost at Sanquelim in Bicholim Taluka.

View Project

Supply, Installation, Testing and Commissioning of flag mast system at the new bridge across river Mandovi at Panaji, Goa

View Project

Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for 4 nos. of Emerson make 30 KVA UPS systems installed for Modular OTs 1-4 at Goa Medical College and Hospital, Bambolim for six months

View Project
x