Project Duration
Stipulated Date of Commencement
Actual Date of Completion October 17 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 132,283,918.00
Awarded for ₹ 156,121,530.72
Final Cost of Project ₹ 166,488,920.00

Project highlights

Upgraded infrastructure for Govt. College at Khandola marcel, Goa

 
Contractors
M/s M V Roa Infra Projects Pvt Ltd
Consultants
M/s. KICONS Limited
 

Sub Works

This project involved 4 sub works. The details of the same available below

1

Interior work.

100% completed
 
Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
October 17 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 31,914,384.00
Awarded for ₹ 31,007,908.28
Final Cost of Project ₹ 30,134,571.00

Project highlights

Providing interior furniture, false ceiling, parttions and other furnishings

 
Contractors
M/s. T. S. Mistry,
Consultants
M/s. KICONS Limited
2

Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Fire Fighting work

100% completed
 
Project Duration
Stipulated Date of Commencement April 08 2014
Stipulated Date of Completion /
Likely Date of Completion
July 07 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,664,951.00
Awarded for ₹ 3,327,405.00
Final Cost of Project ₹ 3,253,496.00

Project highlights

Fire Fighting work

 
Contractors
M/s. Suchi Turnkey Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.
3

Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa – Supply, Installation, Testing and Commissioning of CCTV, Biometric attendance and PA system

100% completed
 
Project Duration
Stipulated Date of Commencement February 24 2014
Stipulated Date of Completion /
Likely Date of Completion
July 07 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,221,634.00
Awarded for ₹ 2,113,317.73
Final Cost of Project ₹ 2,252,110.00

Project highlights

Supply, Installation, Testing and Commissioning of CCTV, Biometric attendance and PA system

 
Contractors
M/s. Reconnoitre Systems
Consultants
M/s. KICONS Pvt. Ltd.
4

Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa -HVAC work

100% completed
 
Project Duration
Stipulated Date of Commencement March 02 2014
Stipulated Date of Completion /
Likely Date of Completion
July 07 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,863,663.00
Awarded for ₹ 2,749,999.50
Final Cost of Project ₹ 3,353,104.00

Project highlights

HVAC work

 
Contractors
M/s. Vighneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.

See Similar Projects

Beautification works in Canacona town within Municipal limits

View Project

Lift work

View Project

Repairs/Upgradation & Maintenance Of Government Schools In The State Of Goa – Civil, Plumbing & Electrical Works – Package-I (Pernem Taluka) – Rate Contract

View Project
x