Project Duration
Stipulated Date of Commencement
October 11 2018
Actual Date of Completion
May 05 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,477,668.00
Awarded for
₹ 15,742,876.00
Project highlights
alteration to the interiors of the existing science block and other miscellaneous works
Contractors
M/S. Deshpande Constructions,
Consultants
M/s. Kicons Limited