Project Duration
Stipulated Date of Commencement
October 31 2012
Stipulated Date of Completion /
Likely Date of Completion November 15 2012
Likely Date of Completion November 15 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,990,517.00
Awarded for
₹ 12,304,125.00
Project highlights
Erection of temporary Hanger for hosting the Inaugural and Closing ceremonies of Internation Film Faestival of India (IFFI) 2012.
Contractors
M/s. Deepali Deisgns & Exhibits Pvt. Ltd.
Consultants
In-house (GSIDC)